Newark campus Master Plan
Interview Issues

  • Retention of the student population through more regional opportunities.
  • Students often park in faculty spaces.
  • Proximity of service road to Hopewell Hall and visibility of dock from LeFevre Hall's main entrance needs improvement.
  • Dangerous vehicular conflict at North entrance.
  • Recognition of donors at South entrance.
  • Improve lighting levels throughout the campus.
  • Walking distance to cars at night is a safety concern.
  • A.D.A. Accessibility.
  • Inadequate walkways.
  • The tennis courts are in a bad location and are in poor condition.
  • Provide an area for the students to congregate outside, in the heart of the campus.
  • Provide more indoor gathering areas on campus.
  • The tables outside of LeFevre and Founders are never used.
  • Poor placement of student amenities.
  • Poor condition of site furnishings.
  • Insufficient recognition for smokers.
  • Lack of recreational opportunities for the students.
  • South meadow needs a land use plan.
  • Too much space is taken in Adena Hall by Physical facilities.
  • Physical Facilities has insufficient space.
  • Improve the student housing to meet current student needs and trends.
  • Improve childcare to meet its current needs and trends.
  • Improve the library to meet student needs.
  • Founders Hall requires renovations.
  • Need for student center.
  • Need for gymnasium space.
  • Cafeteria needs to be upgraded.
  • No "Administration Building".
  • Lack of campus storage.
  • Insufficient space for Science and Chemistry labs.
  • Need for more high tech classrooms.
  • Separation of COTC and OSU records and advising facilities.
  • Shortage of classrooms and office space.
  • Improve the entrances to the campus by providing appropriate image.
  • Enhance the beauty of the campus.
  • Develop outdoor teaching areas.

Site Analysis Issues

  • Possible development of Sharon Valley Road office park tied to a business and industry partnership in open space off Sharon Valley Road.
  • Vehicular circulation within and around campus is a problem.
  • Parking is inadequate and fragmented.
  • Circulation conflicts with service, and pedestrian walkways.
  • More visible entrances would improve the image of campus.
  • Poor and inconsistent building and way-finding signage.
  • Poor pedestrian circulation throughout the campus.
  • Tennis courts location and condition should be addressed.
  • Inadequate student amenities, and poor placement of existing amenities.
  • Poor, inconsistent condition of site furnishings.
  • Appearance of drainage channels and their treatment should be addressed.
  • Inadequate Landscaping.
  • Pond is underutilized.
  • Preserve the central core of campus and keep it green.
  • Improve the flow and process of existing parking areas.
  • Eliminate overhead utilities.
  • Preserve and enhance pleasing views.
  • Develop a consistent architectural style for the campus.
  • Make the campus more bicycle friendly

  Chapter 1 — Introduction
  Chapter 2 — The Newark Campus
  Chapter 3 — Existing Conditions
  Chapter 4 — Goals and Objectives
  Chapter 5 — Alternatives
  Appendix A — Issues

[top]

 

OTHER LINKS
Webmail
WebViewer Events
The Reese Center
COTC Coshocton Campus
COTC Knox Campus
COTC Pataskala Campus
The Business & Industry Institute
Ohio State - Columbus

If you have trouble accessing this page and need to request an alternate format, contact the Webmaster at 740-364-9561.

The Newark campus | 1179 University Drive, Newark OH 43055 | 740-366-1351 | 800-963-9275 | Site Map